Bolton Scout Trust

Bolton Scout Trust Scout Districts

North South East West

 

Index Page

 

April 2006 News letter

 

Meeting Dates

 

Activities Council

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

BIBBY'S FARM NEWS LETTERS

 September / October 2003

 Site Development Progress

A Tender Specification and Bill of Quantities have been prepared. The specification has now been issued to contractors. Discussions have taken placed with a number of them some of them however, having initially said they were interested have now  returned the documents  saying that they are too committed on other work. Further contractors have been contacted   and bids are expected to be available for evaluation by the end of September.

The extent of work will only be finalised when the bids are returned.

It is anticipated that the start of construction will be during October and it has been estimated that it will take 26 -30 weeks to complete.

A newt fence and traps have been installed around the proposed construction site to prevent any great crested newts from venturing into the site. Internal fences and traps have also been constructed within the construction site area. These fences are  required to be in situ for a period of 30 days to trap any potential newts that may be within the site before any construction work can start. During the construction of the internal fences  a Great Crested newt was found. A
bat habitat has also to be erected in what will be the Activity Barn.

 

To control access to the site during construction two temporary gates have been erected one near the entrance to the farm buildings and one leading in to the top field .

 


 

Team A working on fence west of farm in main camping field.

Dave and Brian taking a rest from working on fence east of construction site ( Adjacent to road leading to farm)

For further  pictures  of  Bibbys farm click     Photo Gallery   

Ditch clearing in the bottom field has been completed but will require on going effort to ensure the field is maintained in a dry condition.

Other work carried out recently  has been removal of debris and general site clearance in and around the pig sty, the proposed site of the new canteen. A small barn local to the farmhouse has also been demolished.

 

Site clearance of pig sty area.

Both water and electrical utilities will require upgrading and investigations are underway to determine the most economical way to achieve the required  upgrades

An  outstanding commitment  necessary to ensure full compliance with the planning permission  is the requirement for fencing and landscaping. Approximately 8000 trees require planting  and  a scheme has been submitted to a landscaping company and we are awaiting their estimate and comments.

Fencing specification for  the motorway boundary  is also  under review.

A site brochure is to be produced If anyone out there has good desk top publishing skills and can help please contact  Jack Thompson Tel 01204 841116.